Scope
-
120 MW Open Cycle Gas Turbine Power Plant including a new 66kV Switchyard Connection and a new gas receiving and processing station
-
Management of all engineering, procurement, construction and commissioning activities across all scopes of the project
-
Cost and schedule management to ensure delivery of the project in line with investment decision
-
Performance Testing, verification and handover to plant operations